Gaia IV
Cristo Rei Repowering

Gaia IV project is an important step for us to become self-sustainable in renewable energy. With Cristo Rei hydro power plant repowering, at the Paper Unit, we will make a significant leap towards energy sufficiency, with an increase of 2.55MW to 6.00 MW installed power at the power plant.

Modernization

  • Frequency change from 50 Hz to 60 Hz
  • New transmission line
  • New generation and turbines
  • Infrastructure improvements

Impacts

Power generation
0 %
increase of power plant average generation
0 %
increase in global power average generation

Impacts

Power generation
0 %
increase of power plant average generation
0 %
increase in global power average generation

Investment

Gaia project ongoing expansion has the following expectations:

Estimated investment

R$ 31.299 K

Work execution planned term

18 months

Delivery milestones

Progress

60%

Follow up the project stage macro progress and the expected delivery dates.

20212023StartupDelivery milestonesEnvironmental LicensingIntegrated Environmental StudiesIrani River BasinEngineering and Physical worlsStartup1st2nd3rd4thQuarterQuarterQuarter1st2nd3rd4th1st2nd3rd4th2022
QuarterQuarterQuarter202120222023StartupDelivery milestonesEnvironmental LicensingIntegrated Environmental StudiesIrani River BasinEngineering and Physical worlsStartup1st1st1st2nd2nd2nd3rd3rd3rd4th4th4th

Completed activities

Until 21.02.26, the following stages are in progress:

  • Data survey for Basic project and Environmental Study

Until 21.02.26, the following stages are in progress:

  • New Transmission Line Project

Documents

If you want more details about the Gaia IV project, you can access them through reports and documents. Just download to access the material available.

– RELATÓRIO DE STATUS – GAIA IV Acompanhe as etapas executadas até o momento, as etapas em andamento, os pontos de atenção e oportunidades.