Gaia V
São Luiz Repowering

With new generators and turbines, new transmission line and infrastructure improvements we will be self-sustainable in renewable energy, after the implementation of Gaia V. By means of this, San Luis Hydro power plant repowering, at Unidade Papel SC, will allow an increase from 2MW to 11,5MW of installed power in the power plant.

Modernization

  • Frequency conversion from 50hz to 60hz
  • New transmission line
  • New generators and turbines
  • Infrastructure improvements
  • New engine house

Impacts

Power generation
0 %
increase in powerplant average generation
0 %
increase in global average generation

Impacts

Power generation
0 %
increase in powerplant average generation
0 %
increase in global average generation

Investment

The ongoing expansion, for the Gaia V project, has the following expectations:

Estimated investment

R$ 62.864 K

Planned work execution term

18 months

Delivery milestones

Progress

60%

Follow up the project stage macro progress and the expected delivery dates.

20212023StartupDelivery milestonesEnvironmental LicensingIntegrated Environmental StudiesIrani River BasinEngineering and Physical worlsStartup1st2nd3rd4thQuarterQuarterQuarter1st2nd3rd4th1st2nd3rd4th2022
QuarterQuarterQuarter202120222023StartupDelivery milestonesEnvironmental LicensingIntegrated Environmental StudiesIrani River BasinEngineering and Physical worlsStartup1st1st1st2nd2nd2nd3rd3rd3rd4th4th4th

Ongoing activities

  • Comprehensive Analysis of the Rio do Mato Hydrographic Basin at IMA - Instituto do Meio Ambiente de Santa Catarina.

Documents

If you want more details about the Gaia V project, you can access them through reports and documents. Just download to access the material available.

– RELATÓRIO DE STATUS – GAIA V Acompanhe as etapas executadas até o momento, as etapas em andamento, os pontos de atenção e oportunidades.